Slab casting work 21th floor (K2), Tower - A
Slab casting work 21th floor (K2), Tower - A
Slab casting work 21th floor (K2), Tower - A
Slab casting work 21th floor (K2), Tower - A
Slab casting work 21th floor (K2), Tower - A
Slab casting work - K1 ( 21th floor ) Tower -A
Slab casting work - K1 ( 21th floor ) Tower -A
Slab casting work - K1 ( 21th floor ) Tower -A
Slab casting work - K1 ( 21th floor ) Tower -A
Slab casting work - K1 ( 21th floor ) Tower -A
Slab casting work - K1 ( 21th floor ) Tower -A
Slab casting work - K1 ( 21th floor ) Tower -A
Slab casting work - K1 ( 21th floor ) Tower -A
Slab casting work - K1 ( 21th floor ) Tower -A
Slab casting work - K1 ( 21th floor ) Tower -A
Slab casting work - K1 ( 21th floor ) Tower -A
Tower-B-External Plaster work on progress in Feb. 2022
Tower-B-External Plaster work on progress in Feb. 2022
Tower-B-External Plaster work on progress in Feb. 2022
Tower-B-External Plaster work on progress in Feb. 2022
Tower-A-K1 & K2, 20th Floor Roof Slab work Progress on Jan. 2022
Tower-A-K1 & K2, 20th Floor Roof Slab work Progress on Jan. 2022
Tower-A-K1 & K2, 20th Floor Roof Slab work Progress on Jan. 2022
Tower-A-K1 & K2, 20th Floor Roof Slab work Progress on Jan. 2022
Nov. & Dec. 2021, Brick Work on Progress
Nov. & Dec. 2021, Intl. Plaster Work on progress
Nov. & Dec. 2021, Intl. Plaster Work on progress
Nov. & Dec. 2021, Intl. Plaster Work on progress
Nov. & Dec. 2021, Brick Work on Progress
Nov. & Dec. 2021, MS Railling Work on progress
Nov. & Dec. 2021, MS Railling Work on progress
Nov. & Dec. 2021, MS Railling Work on progress
Tower-A-K1 & K2, 19th Floor Roof Slab work Progress on Oct. 2021
Tower-A-K1 & K2, 19th Floor Roof Slab work Progress on Oct. 2021
Tower-A-K1 & K2, 19th Floor Roof Slab work Progress on Oct. 2021
18th Floor Slab Casting Block K3, K4 & K5 with Intl. Work on Sept. 2021
18th Floor Slab Casting Block K3, K4 & K5 with Intl. Work on Sept. 2021
18th Floor Slab Casting Block K3, K4 & K5 with Intl. Work on Sept. 2021
18th Floor Slab Casting Block K3, K4 & K5 with Intl. Work on Sept. 2021
18th Floor Slab Casting Block K3, K4 & K5 with Intl. Work on Sept. 2021
18th Floor Slab Casting Block K3, K4 & K5 with Intl. Work on Sept. 2021
18th Floor Slab Casting Block K3, K4 & K5 with Intl. Work on Sept. 2021
18th Floor Slab Casting Block K3, K4 & K5 with Intl. Work on Sept. 2021
18th Floor Slab Casting Block K3, K4 & K5 with Intl. Work on Sept. 2021
18th Floor Slab Casting Block K3, K4 & K5 with Intl. Work on Sept. 2021
18th Floor Slab Casting Block K3, K4 & K5 with Intl. Work on Sept. 2021
18th Floor Slab Casting Block K3, K4 & K5 with Intl. Work on Sept. 2021
18th Floor Slab Casting Block K1 & K2 on July 2021
18th Floor Slab Casting Block K1 & K2 on July 2021
18th Floor Slab Casting Block K1 & K2 on July 2021
18th Floor Slab Casting Block K1 & K2 on July 2021
18th Floor Slab Casting Block K1 & K2 on July 2021
18th Floor Slab Casting Block K1 & K2 on July 2021
18th Floor Slab Casting Block K1 & K2 on July 2021
18th Floor Slab Casting Block K1 & K2 on July 2021
18th Floor Slab Casting Block K1 & K2 on July 2021
18th Floor Slab Casting Block K1 & K2 on July 2021
18th Floor Slab Casting Block K1 & K2 on July 2021
18th Floor Slab Casting Block K1 & K2 on July 2021
17th Floor Slab Casting Block K3, K4 & K5 with Railling & Brick Work on Aug. 2021
17th Floor Slab Casting Block K3, K4 & K5 with Railling & Brick Work on Aug. 2021
17th Floor Slab Casting Block K3, K4 & K5 with Railling & Brick Work on Aug. 2021
17th Floor Slab Casting Block K3, K4 & K5 with Railling & Brick Work on Aug. 2021
17th Floor Slab Casting Block K3, K4 & K5 with Railling & Brick Work on Aug. 2021
17th Floor Slab Casting Block K3, K4 & K5 with Railling & Brick Work on Aug. 2021
17th Floor Slab Casting Block K3, K4 & K5 with Railling & Brick Work on Aug. 2021
17th Floor Slab Casting Block K3, K4 & K5 with Railling & Brick Work on Aug. 2021
17th Floor Slab Casting Block K3, K4 & K5 with Railling & Brick Work on Aug. 2021
17th Floor Slab Casting Block K3, K4 & K5 with Railling & Brick Work on Aug. 2021
17th Floor Slab Casting Block K3, K4 & K5 with Railling & Brick Work on Aug. 2021
17th Floor Slab Casting Block K1 & K2 with Intl. Work on June 2021
17th Floor Slab Casting Block K1 & K2 with Intl. Work on June 2021
17th Floor Slab Casting Block K1 & K2 with Intl. Work on June 2021
17th Floor Slab Casting Block K1 & K2 with Intl. Work on June 2021
17th Floor Slab Casting Block K1 & K2 with Intl. Work on June 2021
17th Floor Slab Casting Block K1 & K2 with Intl. Work on June 2021
17th Floor Slab Casting Block K1 & K2 with Intl. Work on June 2021
17th Floor Slab Casting Block K1 & K2 with Intl. Work on June 2021
17th Floor Slab Casting Block K1 & K2 with Intl. Work on June 2021
17th Floor Slab Casting Block K1 & K2 with Intl. Work on June 2021
17th Floor Slab Casting Block K1 & K2 with Intl. Work on June 2021
17th Floor Slab Casting Block K1 & K2 with Intl. Work on June 2021
17th Floor Slab Casting Block K1 & K2 with Intl. Work on June 2021
14th Floor Slab Casting Block K3, K4 & K5, Railling Work & Intl. Work on May 2021
14th Floor Slab Casting Block K3, K4 & K5, Railling Work & Intl. Work on May 2021
14th Floor Slab Casting Block K3, K4 & K5, Railling Work & Intl. Work on May 2021
14th Floor Slab Casting Block K3, K4 & K5, Railling Work & Intl. Work on May 2021
14th Floor Slab Casting Block K3, K4 & K5, Railling Work & Intl. Work on May 2021
14th Floor Slab Casting Block K3, K4 & K5, Railling Work & Intl. Work on May 2021
14th Floor Slab Casting Block K3, K4 & K5, Railling Work & Intl. Work on May 2021
14th Floor Slab Casting Block K3, K4 & K5, Railling Work & Intl. Work on May 2021
14th Floor Slab Casting Block K3, K4 & K5, Railling Work & Intl. Work on May 2021
14th Floor Slab Casting Block K3, K4 & K5, Railling Work & Intl. Work on May 2021
14th Floor Slab Casting Block K3, K4 & K5, Railling Work & Intl. Work on May 2021
14th Floor Slab Casting Block K3, K4 & K5, Railling Work & Intl. Work on May 2021
14th Floor Slab Casting Block K3, K4 & K5, Railling Work & Intl. Work on May 2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
13th Floor Slab Casting Block K3, K4 & K5 & Intl. Work & Navratri Poojan on April'2021
Steel & Railing Material Came at Site (March 2021)
Steel & Railing Material Came at Site (March 2021)
Steel & Railing Material Came at Site (March 2021)
Steel & Railing Material Came at Site (March 2021)
Shuttering Work & Inernal Work in Progress-March 2021
Shuttering Work & Inernal Work in Progress-March 2021
Shuttering Work & Inernal Work in Progress-March 2021
Shuttering Work & Inernal Work in Progress-March 2021
Shuttering Work & Inernal Work in Progress-March 2021
Shuttering Work & Inernal Work in Progress-March 2021
Shuttering Work & Inernal Work in Progress-March 2021
Shuttering Work & Inernal Work in Progress-March 2021
Shuttering Work & Inernal Work in Progress-March 2021
Non Tower Area Shuttering Work in Progress-March 2021
Non Tower Area Shuttering Work in Progress-March 2021
Non Tower Area Shuttering Work in Progress-March 2021
Column Casting for 13th Floor Slab-March 2021
Column Casting for 13th Floor Slab-March 2021
Column Casting for 13th Floor Slab-March 2021
Column Casting for 13th Floor Slab-March 2021
Slab Casting of Non Tower Area-February 2021
Slab Casting of Non Tower Area-February 2021
Slab Casting of Non Tower Area-February 2021
Slab Casting of Non Tower Area-February 2021
Labour Camp Cleanig Work 03.02.21
Labour Camp Cleanig Work 03.02.21
Labour Camp Cleanig Work 03.02.21
Non Tower Area Shuttering Work in Progress-February 2021
Non Tower Area Shuttering Work in Progress-February 2021
Non Tower Area Shuttering Work in Progress-February 2021
Non Tower Area Shuttering Work in Progress-February 2021
Non Tower Area Shuttering Work in Progress-February 2021
Non Tower Area Shuttering Work in Progress-February 2021
Mobilization & Cleaning work at Site 31.01.21
Mobilization & Cleaning work at Site 31.01.21
Mobilization & Cleaning work at Site 31.01.21
Mobilization & Cleaning work at Site 31.01.21
Mobilization & Cleaning work at Site 31.01.21
Mobilization & Cleaning work at Site 31.01.21
Block k1 - brick work has been completed till 16th floor. (18th April 2018)
Block k1 17th floor roof Shuttering work has been done. (18th April 2018)
Block k2- brick work has been completed till 16th floor. (18th April 2018)
Block k3-12th floor roof slab casting has been done. (18th April 2018)
Block k3- brick work has been completed till 7th floor. (18th April 2018)
Railing work has been completed till 3 rd floor of block k4 & k5 (18th April 2018)
Block K5- 11th floor roof slab Shuttering work has been completed (18th April 2018)
K-4, 11th floor roof slab shuttering work (18th April 2018)
K-4, 11th floor roof slab shuttering work (18th April 2018)
K-1 & K-2, 15th floor Brick work has been completed & 16th floor brick work started (18th April 2018)
K-1 & K-2, 4th floor Gypsum plaster work has been completed and 5th floor started (18th April 2018)
K3 10th floor slab casting is in progress on 25 November 2016
K3 10th floor slab casting is in progress on 25 November 2016
K3 10th floor slab casting is in progress on 25 November 2016
K3 10th floor slab casting is in progress on 25 November 2016
K3 10th floor slab casting is in progress on 25 November 2016
K3 10th floor slab casting is in progress on 25 November 2016
K3 10th floor slab casting is in progress on 25 November 2016
K4 - 8th floor shuttering is in progress on October 25, 2016
K4 - 8th floor shuttering is in progress on October 25, 2016
K4 - 8th floor shuttering is in progress on October 25, 2016
K4 - 8th floor shuttering is in progress on October 25, 2016
K4 - 7th floor slab casting is in progress on October 12, 2016
K4 - 7th floor slab casting is in progress on October 12, 2016
K4 - 7th floor slab casting is in progress on October 12, 2016
K4 - 7th floor slab casting is in progress on October 12, 2016
K4 - 7th floor slab casting is in progress on October 12, 2016
Tower A - K-1 - 16th floor slab casting is in progress on October 07, 2016
Tower A - K-1 - 16th floor slab casting is in progress on October 07, 2016
Tower A - K-1 - 16th floor slab casting is in progress on October 07, 2016
Tower A - K-1 - 16th floor slab casting is in progress on October 07, 2016
Tower A - K-1 - 16th floor slab casting is in progress on October 07, 2016
K5- 8th floor column casting is completed on October 03, 2016
K5- 8th floor column casting is completed on October 03, 2016
K5- 8th floor column casting is completed on October 03, 2016
K5- 8th floor column casting is completed on October 03, 2016
K5 7th floor slab casting is in progress on September 22, 2016
K5 7th floor slab casting is in progress on September 22, 2016
K5 7th floor slab casting is in progress on September 22, 2016
K5 7th floor slab casting is in progress on September 22, 2016
Work in Progress as on September 20, 2016
Work in Progress as on September 20, 2016
Work in Progress as on September 20, 2016
Work in Progress as on September 20, 2016
Work in Progress as on September 20, 2016
Work in Progress as on September 20, 2016
Work in Progress as on September 20, 2016
Work in Progress as on September 20, 2016
Work in Progress as on September 20, 2016
Work in Progress as on September 20, 2016
K1 16th floor slab work is in progress on 25-08-16
K1 and K2 16th floor slab work is in progress on 25-08-16
K2 16th floor slab work is in progress on 25-08-16
K3 9th floor slab work is in progress on 25-08-16
K4 6th floor slab work is in progress on 25-08-16
K4 6th floor slab work is in progress on 25-08-16
K5 7th floor slab work is in progress on 25-08-16
K5 Reinforcement of 7th floor slab is in progress on 25-08-16
K5 Reinforcement of 7th floor slab is in progress on 25-08-16
K5 6th Floor Roof Slab Casting as on 2nd July, 2016
K5 6th Floor Roof Slab Casting as on 2nd July, 2016
K5 6th Floor Roof Slab Casting as on 2nd July, 2016
K5 6th Floor Roof Slab Casting as on 2nd July, 2016
K5 6th Floor Roof Slab Casting as on 2nd July, 2016
Work in Progress as on 2nd July, 2016
Work in Progress as on 2nd July, 2016
Work in Progress as on 2nd July, 2016
Work in Progress as on 2nd July, 2016
Work in Progress as on 2nd July, 2016
Work in Progress as on 2nd July, 2016
Work in Progress as on 2nd July, 2016
Work in Progress as on June 15, 2016
Work in Progress as on June 15, 2016
Work in Progress as on June 15, 2016
Work in Progress as on June 15, 2016
Work in Progress as on June 15, 2016
Service Road Work Completed as on June 10, 2016
Service Road Work Completed as on June 10, 2016
Service Road Work Completed as on June 10, 2016
Service Road Work Completed as on June 10, 2016
Work in Progress as on April 12, 2016
Work in Progress as on April 12, 2016
Work in Progress as on April 12, 2016
Work in Progress as on April 12, 2016
Work in Progress as on April 12, 2016
T-K-1 16th Floor Roof Shuttering as on Oct 14, 2015
T-K-1 16th Floor Roof Shuttering as on Oct 14, 2015
T-K-1 16th Floor Roof Shuttering as on Oct 14, 2015
T-K-1 16th Floor Roof Shuttering as on Oct 14, 2015
T-K-5 6th Floor Roof Slab Work in Progress as on Sep 8, 2015
T-K-3 8th Floor Roof Slab Work in Progress as on Sep 28, 2015
T-K-3 8th Floor Roof Slab Work in Progress as on Sep 28, 2015
T-K-5 7th Floor Roof Slab Work in Progress as on Sep 21st 2015
T-K-5 7th Floor Roof Slab Work in Progress as on Sep 21st 2015
Tower K-1 15th Floor Roof Slab Work Started 12th Aug 2015
T K1 & K2 Brick Work Completed Upto 11th Floor 12th Aug 2015
T K-3 & K-4 Brick Work Completed Upto 2nd Floor 12th Aug 2015
Tower K-4 Roof Slab Work on Progress 4th Floor 12th Aug 2015
T K-5 Brick Work Completed Upto on 2nd Floor 12th Aug 2015
Tower K-5 Roof Slab Work on 5th Floor 12th Aug 2015
Tower K-5 Roof Slab Work on 4th Floor 05th July 2015
Tower K-3 Roof Slab Work on 6th Floor 28th June 2015
Tower K-3 Roof Slab Work on 6th Floor 28th June 2015
Tower K-1 & K-2 Roof Slab Work on 14th Floor 9th May2015
T-K-1 & K-2 Brick Work Comleted upto 9th Floor 9th May2015
Tower K-3 4th Floor Roof Slab Casting 9th May2015
Tower K-5 2nd Floor Roof Slab Casting 9th May2015
Construction Are Covered With Green Mesh Net 14th April 2015
Construction Are Covered With Green Mesh Net 14th April 2015
Construction Are Covered With Green Mesh Net 14th April 2015
Tower K-4 G Floor Roof Slab Work In Progress 01st April 2015
Tower K-1 Floor 12A Roof Slab Casted 01st April 2015
Tower K-1/K-2 8th Floor Brick Work Completed 01st April 2015
Tower K-5 1 st Floor Roof Slab Casting Completed 01stApril 2015
Tower K-3 3rd Floor Roof Casteded 28thMarch 2015
Tower K-3 3rd Floor Roof Slab Work Started 10thMarch 2015
Tower K-4 U-Basement Roof Slab Casting Completed 8thMarch 2015
Tower K-1-Corridor Parapet Wall Work Started 8th March 2015
Tower K-5 1st Floor-Roof Slab Work Started 5th March 2015
Tower K-1 Electrical Wall Conduiting Work started 1st March 2015
Tower K-3 2nd Floor Roof Slab Casting 21st Feb 2015
Tower K-1/K-2 6th Floor Brick Work Completed 21st Feb 2015
Tower K-1 12th Floor Slab Casting 18th Feb 2015
Tower K-5 Ground Floor Roof Slab Casting 18th Feb 2015
Tower K-1/K-2 11th Floor Roof Slab Casted 4th Feb 2015
Tower K-5 U.Basement Roof Slab Casted 14th Jan 2015
Tower K-3 2nd floor Roof slab Work Started 14th Jan 2015
K-1, K-2 4th Floor Brick Work Near Completion 14th Jan 2015
Tower K-3 2nd floor Roof slab casting started 6th Jan 2015
Tower K-3 2nd floor Roof slab casting started 6th Jan 2015
Tower K-3 2nd floor Roof slab casting started 6th Jan 2015
Tower K-1, K-2 10th floor casting completed 18th Dec 2014
Tower K-1, K-2 10th floor casting completed 18th Dec 2014
9th floor slab work starts 30th Nov 2014
9th floor slab work starts 30th Nov 2014
8th floor slab work starts 13th Oct 2014
8th floor slab work starts 13th Oct 2014
7th floor slab work starts 19th Sep 2014
5th floor slab Construction full swing 25th July 2014
5th floor slab work starts 22nd July 2014
4th floor slab work starts on 9st July 2014
3rd floor slab work starts on 8st June 2014
2nd floor slab work starts on 21st May 2014
2nd floor slab work starts on 21st May 2014
2nd floor slab work starts on 21st May 2014
2nd floor slab work starts on 21st May 2014
7th May 2014
7th May 2014
7th May 2014
7th May 2014
22nd Feb 2014
22nd Feb 2014
22nd Feb 2014
22nd Feb 2014
22nd Feb 2014
17th Feb 2014
17th Feb 2014
17th Feb 2014
17th Feb 2014
17th Feb 2014
17th Feb 2014
17th Feb 2014
17th Feb 2014
17th Feb 2014
17th Feb 2014
17th Feb 2014
17th Feb 2014
17th Feb 2014
17th Feb 2014